NEV Motor Housing

Product

High-Pressure Die-Cast Aluminum Motor Housing for New Energy Vehicles

Process

Vacuum-Assisted High-Pressure Die Casting (HPDC), 5-Axis CNC Milling, Helium Leak Testing

Customer’s Pain Point

The client encountered recurrent micro-porosity in the thick-walled bearing support sections during standard die casting, leading to coolant cross-contamination under 3-bar hydrostatic testing. Furthermore, thermal distortion post-casting caused the main stator bore coaxiality to drift beyond the 0.05mm threshold, resulting in unacceptable NVH (Noise, Vibration, and Harshness) levels at high RPMs.

Our Solution

Sunmy Hardware engineers conducted advanced Moldflow analysis to optimize gating velocity and implemented a high-vacuum HPDC process to eliminate gas entrapment. To address the porosity in thick sections, we integrated localized squeeze pins into the mold design for active densification during the solidification phase. Post-casting, all critical mating surfaces and bearing bores were machined in a single setup utilizing our 5-axis HAAS CNC machining centers to guarantee strict geometric tolerances and alignment.

Result

The optimized process yielded a 100% pass rate in 5-bar helium leak tests and strictly maintained bore coaxiality within ±0.02mm. We successfully achieved an initial production run of 1,000 pieces with a stabilized 15-day delivery cycle for mass production.